A-Energy put a third well on production
A-Energy put a third well on production
17 June 2018
The third well was completed and put on proction within the second stage of the offshore field development.
This is a dual, oil-producing, horizontal sidetrack well. The length of the main hole is 3800 mand of the side hole is 3763 m. The commissioning of the well boosted the average daily production at the field to the planned level.
The drilling program at the second stage of the field development includes construction and commissioning of 9 wells – 7 production and 2 injection wells – to maintain the planned production level of the field. Earlier in 2018, two wells have been commissioned already – a production well and an injection well.
Within the third stage of the field development a conductor platform is under construction.